York approves 1,014 homes and western station entrance at York Central

Construction is due to start in 2027 on brownfield land west of York station, with first occupation targeted for early 2029 and phase one estimated to finish in 2030.

Leeman Road in York, looking along the carriageway toward a railway bridge with overhead line masts, industrial buildings and fencing beside the York Central corridor.
Leeman Road in July 2025, along the frontage of the York Central site where the council has approved 1,014 homes, a hotel and Central Park. Malcolmxl5, CC0, via Wikimedia Commons

City of York Council’s planning committee granted reserved-matters approval on 10 September 2026 for 1,014 homes, a 213-bedroom hotel and a western station entrance at York Central on Leeman Road.

The decision fixes the largest single phase so far on the 46-hectare outline site west of the city centre. Holgate and Leeman Road sit closest to the railway land where towers and streets will rise over the next four years.

For anyone on the housing wait or commuting through York station, the numbers are concrete: more than 1,000 mixed-tenure homes, including 20 per cent affordable housing, step-free access from the west, and secure cycle storage for at least 300 bikes. Outline permission in 2019 already allowed up to 2,500 homes on York Central; this fifth reserved-matters application covers 10.5 hectares within that footprint.

Open this area on the map
York Central, Leeman Road

What was approved

Application 25/02384/REMM was recommended for approval in the officer report dated 10 September 2026. The approved residential totals are 144 dwellings on Plot E, 508 on Plots F3 and F4, and 362 on Plots K and L, with scheme amendments increasing overall dwellings from 999 to 1,014.

Plot C3 will provide the new western entrance to York railway station, with lift and stair access and a cycle hub holding a minimum of 300 cycles. Plot C4 will host the 213-bedroom hotel. Central Park is described as a linear character area stretching 550 metres through the site. Homes are spread across the Station Quarter, York Yard South and the Foundry Quarter. Building heights were kept down to protect views of York Minster.

Multiple railway tracks and a long red-brick railway building on open land west of York railway station.
Railway land west of York station in 2016, where the approved scheme includes a new western entrance and cycle hub. Ian S, CC BY-SA 2.0, via Wikimedia Commons

Public consultation on this application drew six representations in total, including two objections focused on hotel massing and cyclist access at Coal Drops Square. Planning officers still recommended approval. The Environment Agency did not object, subject to a flood-risk condition.

City of York Council planning officers told the committee the proposals deliver a highly sustainable, well-connected and distinctive mixed-use neighbourhood that responds appropriately to its context, with high-quality streets, parks and landscaping and a significant modal shift away from the private motor vehicle, as reported by BBC News.

Cllr Claire Douglas, leader of City of York Council, said in the National Railway Museum’s announcement:

“This is fantastic news for York. Planning approval for phase 1 of York Central is another major step forward for one of the most significant regeneration projects in our city’s history.”

Tom Gilman, managing director of McLaren Regeneration, said the approval marked a significant milestone in delivering a major addition to York and the wider regional economy.

Tom Bridges, executive regional director for North East, Yorkshire and the Humber at Homes England, said: “With over £135 million of government-funded infrastructure already in place, we now have the foundations to deliver over 1,000 new homes, a new innovation hub and new parks and public space in this first phase alone, and we look forward to seeing this vision become reality as construction gets underway.”

BBC News reported the £135 million infrastructure figure alongside the approval. Mayor David Skaith said: “Soon we’ll see York Central take shape and transform how people see our county.”

What homes sell for nearby

Land Registry records near York railway station show 136 new-build home sales and 902 existing-home sales since 2020, with new builds making up 13 per cent of the total. Sales within 1 km of the station are approximated using postcode sectors YO24 1 and YO1 9; Land Registry data has no distance from the station.

In Holgate in 2024, the median price paid was £235,500 for houses across 84 sales and £177,500 for flats across 37 sales.

Holgate is approximated with postcode sector YO26 4; ward boundaries do not match postcodes exactly. From 2022 to 2024, the median for houses in Holgate was £229,500 across 250 sales, about 18 per cent above the £195,000 median across 301 house sales from 2019 to 2021.

Medians for Holgate houses rose from £187,000 in 2019 to £235,500 in 2024 before edging down to £230,000 in 2025 in Land Registry records, with the steepest year-on-year gains coming after 2021.

Median price paid for houses, Holgate, 2019 to 2025

Source: HM Land Registry Price Paid Data

In 2024, flats accounted for 16 per cent of the 532 home sales on the station side of York and 8 per cent of the 569 home sales in Holgate, though HM Land Registry Price Paid Data lag by about two months, so recent months are incomplete.

Background

York Central is a strategic brownfield allocation west of York station.

Outline planning permission 18/01884/OUTM was granted in 2019 for up to 2,500 homes and up to 379,729 sq m gross external area of mixed-use floorspace.

Earlier reserved matters secured spine roads, National Railway Museum Central Hall, Museum Square and a Government Property Agency office building.

Application 25/02384/REMM is the fifth reserved-matters submission and the first to include this scale of housing plus the western station entrance, hotel and Central Park.

Grade II listed gatepiers and gates to the former York goods station on Leeman Road, with York railway station visible beyond.
The York goods station entrance on Leeman Road in 2023, near the area earmarked for the western station entrance. Malcolmxl5, CC BY-SA 4.0, via Wikimedia Commons

What happens next

Site investigation works are due to begin imminently. Construction is scheduled to start in 2027, with first occupation targeted for early 2029 and phase-one completion during 2030, the National Railway Museum said.

City of York Council executive members were due to meet on 6 October 2026 to consider land disposals linked to the same reserved-matters application, including Fermetol Trading Estate where every home on that parcel is to be affordable housing.