Wirral backs £36.5m Borough Yard works as Birkenhead new-build sales dry up

John Sisk & Son's £36.5m enabling contract aims to unlock at least 633 homes, but CH41 recorded no new-build sales in the latest year.

Railway tracks and Birkenhead Central station buildings seen from the disused Mollington Street bridge, with a derelict train shed beside the line.
Railway tracks and Birkenhead Central station buildings seen from the disused Mollington Street bridge, with a derelict train shed beside the line. Rodhullandemu, CC BY-SA 4.0, via Wikimedia Commons

Wirral Council’s policy and resources committee approved a £36.5m fixed-price contract with John Sisk & Son on 18 November 2026 for primary enabling works at Borough Yard in Birkenhead, as new-build homes made up 2.6 percent of CH41 sales in calendar 2024.

Hybrid planning consent granted in October 2025 covers up to 1,600 homes over 10 to 15 years on former gasworks and railway land between Birkenhead Central and Green Lane stations. The council expects the enabling programme to support delivery of at least 633 homes.

Land Registry records show 9 new-build sales among 348 CH41 home sales in calendar 2024, down from 20.6 percent (93 of 452 sales) in calendar 2022. Those figures cover CH41, the postcode district around Borough Yard and Birkenhead town centre, before any completions from the remediated gasworks site reached the register.

A committee report said not going ahead could put funding at risk, including £2.6 million already drawn down from Homes England.

Where new-builds stopped

CH41 recorded no new-build sales among 695 homes sold from October 2025 to September 2026. Borough Yard completions are not yet visible in these records.

In CH41, the new-build share was 18.0 percent in calendar 2021 and 11.8 percent in calendar 2023, before falling to 2.6 percent in calendar 2024.

Birkenhead new-build sales dried up before Borough Yard: percent of CH41 sales, by calendar year

Source: HM Land Registry Price Paid Data

Across Wirral, new-builds made up 0.3 percent of the market, with 14 sales among 4,384 homes in the same 12 months to September 2026. The North West stood at 1.7 percent, with 1,245 new-build sales among 73,074 homes, and England at 2 percent, with 13,212 among 676,259.

Far below the Wirral price

Homes that did sell in CH41, Birkenhead traded far below Wirral as a whole. Land Registry records for CH41 in the 12 months to September 2026 show a median price paid of £114,000 across 695 sales, against a Wirral median of £215,000 across 4,384 sales.

The North West median was £213,000 across 86,455 sales and England’s £285,000 across 676,259 sales in the same window.

In CH41, flats sold for a median of £97,500 across 44 sales, below terraced homes at £105,000 across 181 sales.

What £36.5m leaves out

Construction News reported that the estimated cost of the wider enabling programme rose from £57.1m to £66m, citing inflation, programme delays and drainage costs. Liverpool City Region Combined Authority approved a funding reallocation on 6 November 2026 to cover the shortfall.

Under the fixed-price deal, Sisk will remediate and engineer the ground, build an active travel corridor and deliver part of the Dock Branch South linear park.

Sewer diversions, an underground stormwater storage tank and associated drainage infrastructure sit outside the contract, on a separate £13.7m budget delivered with United Utilities. Cadent gas relocation works are also separate. Kings Square highway realignment and most of the linear park, about £11.8m, were stripped from Sisk’s initial scope.

Green Party Cllr Gail Jenkinson told Wirral Council’s policy and resources committee on 18 November that the scheme mattered for brownfield land across the borough.

“We absolutely have to protect our brownfield developments and so this is such a major project going forward. By protecting the brownfield we also protect the green belt.”

The council also approved an estimated £2.9m development management contract with Ion Property Developments. The Wirral Globe reported that a further £8.9m is now required.

Conditions first, then 2027

Wirral Today said some planning conditions still need to be met before enabling works can begin. The Wirral Globe said outline planning permission for the scheme, which includes the demolition of two flyover roads near Birkenhead Central, was granted in early 2025.

Open this area on the map
Borough Yard, Birkenhead

Housing is planned on Borough Yard, the site between Birkenhead Central and Green Lane stations. Deferred Kings Square and linear park works are expected from April 2027 or later.