Liverpool Waters loses about 2,000 homes in revised dock plan

Peel's approved masterplan allows up to 5,836 homes on the northern docks and will guide development to 2041.

Princes Dock water basin with Alexandra Tower and waterfront offices, seen from above.
Princes Dock, Liverpool Waters, seen from the air. Rodhullandemu, CC BY-SA 4.0, via Wikimedia Commons

On 24 November 2026 Liverpool City Council approved Peel Waters’ revised Liverpool Waters masterplan, cutting about 2,000 homes from the 2013 outline.

Land Registry records show new builds were 9.3 percent of 248 L3 sales in the 12 months to September 2026.

The committee vote on 24 November 2026 fixed what can be built on Liverpool Waters: homes under the revised masterplan are now capped at up to 5,836, including 20 percent affordable housing, across five neighbourhoods from Princes Dock to the Northern Docks. That is about 2,000 fewer than the 2013 outline consent allowed on the 60-hectare northern waterfront.

The 7,111 homes in pre-committee papers add that 5,836 ceiling to just shy of 1,300 homes Peel said were already delivered under standalone consents since 2013.

About 8 million sq ft less

Homes were not the only element trimmed. Place North West said the revised plan cuts about 8 million sq ft from the 2013 ceiling, including 2 million sq ft of offices and shops, restaurants and bars from 880,000 sq ft to 277,000 sq ft.

Place North West said parking provision falls by 3.5 million sq ft in the same revisions.

Open this area on the map
Liverpool Waters, Princes Dock

Stadium, sewer and demand

Peel Waters blamed three forces for the shrinkage: shifting demand since 2013, Everton’s Hill Dickinson Stadium on dockland once earmarked for housing, and the Mersey Estuary Pollution Alleviation Scheme sewer, which limits what can be built at Clarence Dock.

Chris Capes, development director at Peel Waters, said the update was meant to stay relevant for a new generation of waterfront living.

“It creates a more deliverable framework for future growth that responds to changing economic, environmental and social priorities.”

New-build sales thin out

New builds made up 9.3 percent of L3 home sales in the 12 months to September 2026, against 56.3 percent in calendar 2019, when waterfront apartment completions pushed the share unusually high.

New-build share of L3 home sales fell from calendar 2019 to 12m to Sep 2026: share of homes sold

Source: HM Land Registry Price Paid Data

In the same period, flats were 216 of 248 L3 sales at a median of £165,816. Liverpool flats sold for a median of £135,000 across 1,014 sales, one in five of the city’s 5,348 home sales.

Across Liverpool, Land Registry records show a median of £168,000 across 5,348 sales; the North West median was £213,000 across 121,512 sales and England’s median was £285,000 across 676,259 sales.

Liverpool recorded 44 new-build sales, 1 percent of city sales in that period.

A park by spring 2028

Peel is already spending £81.1 million on infrastructure at Central Docks, making space for up to 2,350 new homes and commercial floorspace. Place North West said a five-acre waterfront park with more than 3,000 trees is under construction and due to open in spring 2028, alongside the Peel-funded Mersey Heat district energy network and new active travel links.

James Whittaker, managing director of Peel Waters, said the approval “marks another major milestone in the transformation of Liverpool’s northern waterfront.” Further neighbourhood masterplans and reserved matters applications will follow under reference 24F/1916 through to 2041.