North Somerset Full Council met on 10 November 2026 to consider borrowing of up to £9.5 million after the Banwell Bypass budget was forecast to rise and the opening date slipped 28 weeks.
The North Somerset Post reported that council papers put the forecast budget rising from £105.176 million to about £114.7 million. Completion is now set for 23 December 2027, against a previous target of 8 June 2027. The figure councillors were asked to borrow matches the gap between those forecasts while the council challenges costs and seeks recovery.
The Post said utility costs were revised from £4.151 million to £6.835 million, with indicative delay-related compensation events put at £5.320 million. Those lines account for most of the extra £9.5 million. Galliford Try remains the contractor, but the council report states that mitigation opportunities have been exhausted.
Tied to 7,557 homes
The 2020 Housing Infrastructure Fund bid tied the bypass to delivering 7,557 new homes. The executive summary counted 4,482 at existing Weston Villages sites including Haywood Village and Locking Parklands, with the remainder through the Local Plan.
Homes England is funding £88.43 million of the scheme and North Somerset Council £16.746 million. Council leader Mike Bell called it “a project with a 100-year history, set to finally tackle notorious traffic congestion in the narrows of Banwell village”.
New builds sit in the villages
Land Registry records show new homes are already trading heavily around the Weston growth sites. In calendar year 2024 the Weston Villages and Locking postcode district recorded 150 new-build sales out of 604 home sales, a 25 per cent share.
The median price paid there was £284,995 on those 604 sales. Haywood Village’s median was £280,000 on 315 sales in 2024.
Shares outside the villages
In the 12 months to September 2026, Banwell recorded a 29 per cent new-build share on 59 sales at a median of £355,000.
In calendar year 2024 the BS24 postcode district, which covers Weston Villages and Locking, recorded a 25 per cent new-build share on 604 sales at a median of £284,995.
In the 12 months to September 2026, Weston-super-Mare stood at a 1.6 per cent share on 1,572 sales at a median of £260,000. Across North Somerset the share was 2 per cent on 3,295 sales at a median of £313,500.
Across the South West, Land Registry records show a 1.6 per cent new-build share on 58,186 sales in the 12 months to September 2026, at a median of £277,500. Across England in the same 12 months, new builds were a 2 per cent share at a median of £285,000 on 676,259 sales.
Source: HM Land Registry Price Paid Data
Banwell is dearer, on fewer sales
Homes in Banwell sell for more, though on far fewer sales. In the 12 months to September 2026 the median price paid was £355,000 on 59 sales.
Seventeen of those 59 sales were new builds, a 29 per cent share of the year’s transactions.
In calendar year 2024 within Banwell’s postcode district, new builds sold for a median of £320,044 on 114 sales and existing homes for £295,000 on 57 sales.
The grant deadline comes first
The council still targets a 23 December 2027 opening, but the Homes England grant must be claimed by the end of March 2027.
The report estimates £1.2 million to £2.75 million may be unclaimable. In the worst case the extra money needed could reach £12.249 million before savings.
Any unrecovered borrowing could cost the council up to £0.9 million a year from the 2028/29 financial year. Legal advice may cost £300,000 to £400,000.
Mike Bell, leader of North Somerset Council, said:
“Despite delay we continue to make good progress on site and the century-long wait will soon be over.”
The council will ask Homes England to extend the grant claim deadline.